← All articles

Project Baselines: What They Are and Why They Matter

By XNM Technologies · July 15, 2022 · 3 min read
Project Baselines: What They Are and Why They Matter

A project baseline is the approved, fixed reference point against which actual project performance is measured. In project management, there are typically three baselines: the scope baseline (what will be delivered), the schedule baseline (when it will be delivered), and the cost baseline (how much it will cost). Together, these three form the performance measurement baseline -- the foundation of earned value management and the basis for all project performance reporting.

A baseline is not the same as a plan. A plan is a working document that is updated as the project proceeds. A baseline is frozen -- it does not change unless a formal change control process is followed. The baseline represents what was approved and committed to; the plan represents current thinking about how to get there.

Why Baselines Matter

  • Without a baseline, there is no objective way to measure whether a project is on track. If you do not know what you planned to accomplish by a given date and at what cost, you cannot determine whether you are ahead of schedule, behind schedule, under budget, or over budget.

  • Without a baseline, scope creep is invisible. Scope creep -- the gradual, uncontrolled expansion of project scope -- is one of the most common causes of project overruns. A scope baseline makes additions to scope visible as deviations from the baseline, triggering change control.

  • Without a baseline, forecasting is guesswork. Earned value management, which uses the relationship between planned value, earned value, and actual cost to forecast project completion, requires a stable baseline to calculate meaningful forecasts.

The Three Baselines Explained

  1. Scope baseline. The approved project scope, including the Work Breakdown Structure (WBS) and WBS dictionary. The scope baseline defines what is in scope and what is out of scope. Any addition or removal of scope must be processed through change control and, if approved, the scope baseline is updated.

  2. Schedule baseline. The approved project schedule, showing the planned start and finish dates for each activity, milestone, and deliverable. The schedule baseline is the reference for reporting schedule variance and forecasting completion.

  3. Cost baseline. The approved time-phased budget for the project, showing how costs are planned to be incurred over time. The cost baseline is the reference for reporting cost variance and forecasting cost at completion.

How to Establish a Baseline

A baseline is established when the project plan has been reviewed, approved by the relevant stakeholders, and formally authorised. The baseline should not be established too early (before adequate planning has been done) or too late (after work has begun, which means the baseline cannot reflect actual pre-work status). In practice, the baseline is established at the end of the planning phase, before execution begins.

Changes to the baseline after establishment must go through formal change control. Informal changes -- adjusting dates, adding scope, or increasing the budget without formal approval -- undermine the baseline's integrity and make performance measurement unreliable.

XNM provides project management advisory to public-sector and capital-project clients, including baseline establishment and performance measurement. Reach out to XNM's program & project delivery advisory team to discuss project baselines and performance measurement for your project.